Thank you to Jen Roth, principal at Charlotte Central School, for providing this update on the construction at CCS.
Here are some new details about the work happening around CCS for the last two weeks. Behind the scenes, I’d like to thank our entire custodial crew (May, Audrey, Ester, Jeremy, Alex, Mike H., Jack S. and Mason M.) for using every possible minute to polish up spaces in the building to make it safe and welcoming for everyone.
The placement of the water storage tanks has been completed. Concrete is getting poured to start building out the new utility room and to add the foundation from the front porch on the 1939 building.
Crews are updating the utility access to the front of the building and running conduit through the first floor of the building.
Second Floor classrooms are nearly polished. Carpets have been installed in the planned spaces. Some painting has been completed to brighten things up. Worn down shelves were given a coat of paint where possible. Final touches to the second floor will include waxing the green hallway, shampoo the carpets and finalizing any IT installations.
The bus parking lot is coated with blacktop and setting. The last step is to paint the lines to be ready for the buses.
No comments:
Post a Comment
Thank you for leaving a comment on our blog. We don't respond to comments and instead use our blog as a way of sharing our district's story and updates.
If you'd like to leave us a comment, we will see it. However, if you'd like a response, please reach out using the link on the right side of this post that says "Connect Now".
Thank you!